Pinehaven culvert replacement

Published on 04 June 2021

Pinehaven Road Intersection.JPG

Work to upgrade two culverts within the Pinehaven Stream that form the road crossings on Sunbrae Drive and Pinehaven Road is scheduled to begin on Tuesday 8 June 2021. Downer is carrying out this work.

The existing culverts are at the end of their design life and are to be replaced with larger culverts and headwalls that meet current seismic and roading standards.

Stage 1 - Single lane only
Start date: 8 June 2021
Duration: Approximately four weeks

The first stage of this work will be to relocate the services such as telecommunications, and water that cross within the area to be excavated. During this time there will be single lane traffic management in place with a stop/go operating.

We estimate that this stage will take approximately four weeks from 8 June. Please be aware that there might be minor delays and factor this into your journey planning. Pedestrian access will still be available.

Stage 2 - Road closure
Start date: early July
Duration: Approximately three months

To find out more about stage 2, go to our project webpage Roading: Pinehaven Culvert Replacement.